Working alongside Bakkavor for many years we were asked to quote to replace 4no existing loading bays which were beyond repair. This project required removal of 4 doors, frames, dock levellers and then installation of 4 new insulated sectional overhead doors including frames and 4no dock levellers. Usually this would be a straightforward project but we had to work with 2 bays at a time allowing full production to carry on as normal. This was achieved through creating a temporary wall at the back of the loading docks to maintain a clean area and retain the loading dock chilled temperature.